Weekly WIP Reports: Five Numbers That Predict a Late Shipment
Five weekly WIP numbers that show a late apparel shipment early: cutting, lines started, output, rework and trim arrival.

Answer first: A weekly work-in-progress (WIP) report is useful when it contains five numbers that can be compared with the plan: cutting completion, the quantity actually started on the line, daily output, rework, and whether the trims for that style have arrived. Those five figures tell you whether a shipment is sliding before the ex-factory date moves. A photograph of a busy floor, or a message that “production is ongoing,” does not. This article defines the five numbers, a simple report format, warning signs, and the usual counters. The thresholds below are a practical reading for buyers, not published Finetex key performance indicators, and not a promise about any one factory’s current orders.
Finetex’s published bulk window is 15–45 days from deposit and an approved pre-production sample, depending on quantity, fabric availability and trim lead times, as stated on the quality control and site FAQ pages. What sits inside that window is explained in our guide to what drives production lead time. A WIP report is how you see, week by week, whether that window is still real.
The five numbers, and what each one actually means
WIP is not a single pile of garments. It is the work that has been released into the factory and has not yet been packed. For a cut-and-sew knit order, five quantities are enough to see a slip early. Report each one as a number against the order quantity, not as a colour or a traffic light on its own.
| Number | Definition | Why it predicts a late shipment |
|---|---|---|
| 1. Cutting completion | Cut panels issued, as a percentage of the order (or of the weekly cutting plan), by size and colour | If cutting is late, sewing cannot catch up without overtime or a reduced quantity. A “cut 80 percent” figure that hides one missing size is also a delay. |
| 2. Quantity started on the line | Pieces that have actually begun sewing, not only pieces that have been cut | Cut work sitting in a bundle rack is not production. A gap between cut and started is a line-loading or bottleneck problem. |
| 3. Daily output | Finished pieces off the line per working day, against the rate the plan assumed | This is the number that shows whether the remaining days can still cover the remaining pieces. |
| 4. Rework rate | Pieces sent back for repair, as a percentage of pieces sewn in the week, plus a note of the main defect | Rework consumes the same line time as first-quality output. A rising rate late in the run is how a “green” output number still misses the ship date. |
| 5. Trim arrival | Whether the trims required for this style — thread, labels, buttons, elastics, packing — are in house, by item, with the date received or the outstanding date | A complete cut is useless if the neck label, the carton sticker or a button is still on the water. |
Two rules make the five numbers honest. First, they must refer to the same style, colour and purchase order; a factory-wide output figure hides the late style. Second, they must be dated. A weekly report without a report date, a plan date and the agreed ex-factory date is a snapshot you cannot compare with the next week.
Cutting completion should be based on issued panels, not on a marker that has been plotted but not cut. Quantity started should be based on the first sewing operation, not on bundles moved next to the line. Daily output should be first-quality pieces that have passed in-line, or a clearly stated definition that is used every week; mixing repaired pieces into “output” without a note is how rework is disguised. Trim arrival should be a line-by-line list, not a single yes.
A report format that a small buyer can actually read
You do not need a factory ERP export. You need one page, sent on the same day each week, that a merchandiser can check in a few minutes. A usable format is:
- Header: purchase order, style, colour, order quantity, report date, plan ex-factory date, and the factory contact.
- A five-row table with planned value, actual value, and variance for each of the five numbers.
- A short comment only where a variance exists: the reason, the counter, and the new date if the ex-factory date is at risk.
- Optional evidence: a photo of the cut bundles or of the trim shelf is useful only when it is labelled with the same order number. Unlabelled floor photos do not add information.
Keep units consistent. If cutting is reported in pieces, do not report output in dozens in the same file. If the order is mixed sizes, add a size breakdown for cutting and for output once a week; a shortage in one end size is a late carton, even when the total percentage looks acceptable.
A mid-order example, for illustration only and not a Finetex result, might read: order 2,000 pieces; cutting 100 percent; started 1,400; daily output 220 against a plan of 250; rework 4 percent, mainly a broken stitch at the armhole; main label in house, carton stickers due in three days. The story in that line is not “production started.” It is that output is already below plan, rework is using line time, and one packing trim is still outstanding — enough to ask a question this week, not after the goods miss the vessel.
Warning signs, stated as advice
Thresholds have to be set against the remaining calendar, not against a universal percentage. A 10 percent output shortfall in week one of a long run is a conversation; the same shortfall in the last five days is a missed ship date. The signs below are a buyer’s checklist, not a published factory scorecard.
- Cutting still incomplete inside the last third of the sewing window. There is no spare time to recut a wrong size or a shade issue.
- A widening gap between cut pieces and pieces started. Bundles are accumulating, which usually means a line is not free, a trim is missing, or a quality hold is not being named.
- Daily output below the rate needed to finish on the remaining working days, for two reports in a row. One soft week can be overtime; two is a plan change.
- Rework rising as the line speeds up. This is often a new operator, a skipped in-line check, or a machine setting that was not corrected at the 30 percent inspection point.
- Any critical trim still outstanding after cutting is complete. Labels, buttons and packing materials have no substitute on the ship date.
These signs should be read with the quality gates on our quality control page. An in-line check at 30 percent and at 70 percent is there to catch stitch and tension problems while the run can still be corrected. If the WIP report shows rising rework and there is no in-line report, the quality system and the planning system are both slipping.
Chinese New Year and other calendar closures change the remaining working days, which is why a WIP report should show working days left, not only calendar days. Our Chinese New Year production calendar is the place to set those cut-offs; the weekly numbers are how you see whether you are still on the right side of them.
Counters that usually work, and ones that do not
When a number is off, the useful response is specific.
- If cutting is late, ask whether fabric, shade continuity or marker approval is the hold, and whether a partial cut of complete sizes can be started without mixing dye lots. Incomplete sizes should not be sewn just to show a higher “started” figure.
- If started lags cutting, ask which operation is the bottleneck and whether a line has actually been assigned to this style.
- If daily output is below plan, ask for the remaining working days, a realistic daily rate, and whether overtime or an extra line is actually available — not only promised.
- If rework is rising, ask for the defect and the operation, and tie it to the in-line check. Retraining a named operation is the method described on our quality page; “the line will try harder” is not.
- If a trim is late, ask for the supplier date, a substitute that you have approved in writing, or a decision to ship a complete colourway rather than wait for a whole order.
Counters that rarely recover a late date include adding a new untested subcontractor in the last week, changing the fabric lot to keep the line moving, and packing incomplete sizes to “make the shipment.” Each of those creates a quality or customs problem that costs more than a revised ex-factory date.
A one-page template you can request with the purchase order
Put the WIP requirement in the order file, not in a follow-up email after you start to worry. A short clause is enough: a weekly report on an agreed weekday, in the five-number format, from the merchandiser who owns the order, starting when fabric is in house or when cutting starts, whichever you specify.
| Field | Planned | Actual this week | Variance and comment |
|---|---|---|---|
| Cutting completion (pieces / %) | |||
| Quantity started on the line | |||
| Daily output (pieces / working day) | |||
| Rework rate and main defect | |||
| Trim arrival (item, date in house or outstanding) | |||
| Working days left to ex-factory |
Ask for the first report in the same week cutting starts, so you have a baseline, and keep the previous week’s file. The value is in the comparison, not in a single perfect form. If a factory cannot produce these five numbers, that is itself information about how the order is being run.
For onboarding and for the wider planning file, start from the clothing factory sourcing guide. The WIP report does not replace a social audit, a quality plan or a lead-time discussion; it is how those plans are checked while the order is alive.
What is fact, what is advice and what is uncertain
Fact: Finetex’s published bulk lead time is 15–45 days from deposit and an approved pre-production sample, with the drivers described in the lead-time article and the quality gates described on the quality-control page. Sampling times are 5–7 working days for a development sample and 10–12 working days for a size set.
Advice: the five numbers, the warning signs, the counters and the template are our practical reading for buyers. They are not published Finetex KPIs and not a contractual service level.
Uncertain: the output rate a given style will actually hold depends on the fabric, the operations and the line assignment. A plan rate should be confirmed in writing when the order is accepted, then checked against the weekly report.
Related reading
- Chinese New Year Production Calendar: 2027 Cut-Off Dates
- Factory Audit Types: BSCI, Sedex, WRAP and What Each Proves
- China vs Vietnam for Apparel Manufacturing: Duty, Lead Time and Minimums
- Building a Landed Cost Sheet: FOB, Freight, Duty, Fees
Frequently asked questions
How often should I receive a WIP report?
Weekly, on the same weekday, once cutting has started — or once fabric is in house, if you want to see trim and fabric holds earlier. Daily reports help only in the last few days before ex-factory, and only if the five numbers stay defined the same way.
What if the factory sends photos instead of numbers?
Ask for the five figures against the plan, with a date. Photos can support a number; they cannot replace it. An unlabelled floor photograph does not tell you whether your style is on the line.
Is rework already included in daily output?
It should not be, unless the factory says so clearly. First-quality output and repaired pieces have to be stated separately, or you will miss the line time that rework is using.
Can a WIP report change the published 15–45 day bulk window?
The window is a range that depends on quantity, fabric and trims. The report does not change that range; it shows whether your specific order is still inside the schedule you agreed on the purchase order.
Sources
- Finetex: Quality control
- Finetex: What drives production lead time
- Finetex: Clothing factory sourcing guide
- Finetex: Chinese New Year production calendar 2027
Ask for a weekly WIP format with your order
Tell us the style, the quantity and the ex-factory target. We will confirm the schedule in writing and can report cutting, line start, output, rework and trim arrival on an agreed weekday while the order is in production.
Request a quote or read how quality is checked on our quality control page.
More factory-floor notes for brand owners

Selling Underwear in Germany: Textilkennzeichnung, LUCID and Packaging Law
German textile labelling, LUCID registration and packaging law for underwear brands after the PPWR and VerpackDG took effect…
Read more →
GSM to Ounce Converter and Fabric Weight Chart
Convert fabric weight between gsm and oz/yd² with the exact factor (1 oz/yd² = 33.906 g/m²), a T-shirt…
Read more →
First-Output Check: The In-Line Inspection That Saves Bulk
What to check on the first garments off each line: measurements, seams, labels and print against the approved…
Read more →
A Fit Session Protocol for Knit Tops: 12 Wearers, 5 Measurements
A recommended fit session protocol for knit tops: recruit 12 wearers, take five measurements, run a movement checklist,…
Read more →
Corporate Uniform Programs: Tendering, Sizing and Reorders
How to run a corporate uniform program with a factory: tender documents, sizing a workforce, producing many sizes…
Read more →
Muscle Fit and Athletic Fit T-Shirts: Pattern Changes That Matter
How muscle fit and athletic fit T-shirts differ from a classic block: chest-to-waist drop, sleeve cap and bicep,…
Read more →Request a sample & pricing information
Send us your tech pack, target price or a reference sample — we reply with a quotation, a realistic lead time and a fabric recommendation within one working day.
- Free sampling plan & cost breakdown
- MOQ from 300 pcs per style
- Reply within 1 working day