Chinese New Year Production Calendar: 2027 Cut-Off Dates

China's official 2027 Spring Festival holiday runs 5–13 February. Work back from it: order, sample, bulk and shipping cut-offs plus 90/60/30-day reminders.

Chinese New Year Production Calendar: 2027 Cut-Off Dates

Answer first: China’s official 2027 Spring Festival holiday runs from Friday 5 February (New Year’s Eve) to Saturday 13 February, with Sunday 31 January and Sunday 14 February as make-up working days. For apparel orders that must ship before the break, approve pre-production samples and pay deposits by early December 2026, and aim to load goods by late January 2027.

Chinese New Year is the one fixed event that every apparel order made in China has to plan around. Factories close, many workers travel home, mills and trim suppliers stop, and freight space tightens before the break. This calendar takes the official 2027 holiday dates, published by the General Office of the State Council on 5 November 2026, and works backwards to the decisions a buyer has to make. It uses Finetex’s published sampling and bulk lead times as the example; your supplier’s figures may differ, so replace them with the ones in your own quotation.

The official 2027 holiday dates

The State Council notice (国办发明电〔2026〕10号) sets the 2027 Spring Festival arrangement as follows:

DateDayStatus
31 January 2027SundayMake-up working day
5 February 2027FridayHoliday begins (New Year’s Eve, 除夕)
6 February 2027SaturdayChinese New Year’s Day (正月初一)
13 February 2027SaturdayLast day of holiday (正月初八)
14 February 2027SundayMake-up working day; offices reopen
20 February 2027SaturdayLantern Festival (正月十五), not a public holiday

The notice gives nine days of holiday. The same notice sets the other 2027 holidays, including Labour Day (1–5 May) and National Day (1–7 October), which are useful for planning the rest of the year.

Why the official dates are not the whole story

The official holiday is the minimum closure. In knitwear manufacturing, production capacity usually falls before the holiday and returns gradually after it, because many workers travel long distances to their home provinces and some take extra days. Mills, dye houses and trim suppliers follow their own schedules, and a factory cannot sew a garment whose fabric or elastic is still at a supplier that closed early.

We do not publish an industry-wide “real” closure length, because it varies by region, factory and year. The practical approach is to ask each supplier for three dates in writing: the last day it will accept material deliveries, the last day it will load finished goods, and the date it expects lines to run at normal output again. Plan with those dates, not with the public holiday alone.

Work backwards from the last loading date

The table below works backwards from an example last loading date of Friday 22 January 2027, two weeks before New Year’s Eve. That buffer is an assumption, chosen because ports, trucking and forwarders become congested in the final days before the break. Replace it with your supplier’s confirmed date.

Also check:  What Are the Best Wholesale Plus Size Clothing Manufacturers in China: How to Read the Lists (and What They Leave Out)
MilestoneExample dateBasis
Goods loaded ex-factoryFri 22 Jan 2027Assumed buffer before 5 Feb
Final inspection bookedMon 18 Jan 2027A few days before loading
Bulk start, smaller order (15-day bulk)Thu 7 Jan 2027Finetex bulk lead time lower end
Bulk start, larger order (45-day bulk)Tue 8 Dec 2026Finetex bulk lead time upper end
Deposit paid and pre-production sample approvedSame as bulk startBulk lead time runs from both
Size set approvedAbout two weeks before PP approval10–12 working days for a size set
Development sample approvedMid-November 2026 for most programmes5–7 working days per sample round

Finetex’s published lead times are: development or fit sample 5–7 working days after artwork and fabric are confirmed, a graded size set 10–12 working days, and bulk production 15–45 days from deposit and approved pre-production sample, depending on quantity, fabric availability and trim lead times. A custom dye lot or knit can lengthen the fabric stage. Our production lead time article explains what moves an order between the short and long end.

The 90/60/30-day reminder plan

Counting back from New Year’s Eve, Friday 5 February 2027:

  • 90 days (Saturday 7 November 2026): decide the range. Confirm which styles must arrive before spring and which can wait for a post-holiday run. Send tech packs and quantities.
  • 60 days (Monday 7 December 2026): lock bulk. Approve pre-production samples, confirm fabric and trims, pay deposits and book freight. For orders with a long bulk window, this is the latest practical date.
  • 45 days (Tuesday 22 December 2026): confirm the factory’s holiday schedule. Get the last material, last loading and restart dates in writing.
  • 30 days (Wednesday 6 January 2027): check progress. Review cutting and sewing completion against plan. If an order is at risk, decide now between air freight, a partial shipment or a post-holiday shipment.
  • 14 days (Friday 22 January 2027): load. Final inspection and loading for the last pre-holiday sailing.
  • 7 days (Friday 29 January 2027): stop expecting movement. Treat anything not loaded as a post-holiday shipment.

Today’s date matters: if you are reading this after early December and have not approved samples, assume your bulk order will ship after the holiday and plan the launch around that.

Shipping before and after the break

Freight demand rises before the holiday as factories try to clear finished goods. Book space early and keep documents ready, because a missing certificate or packing list error is harder to fix when offices are closing. As a reference, Finetex publishes typical transit times of 18–22 days by sea and 9–11 days by air to the US West Coast, 22–28 days by sea to the US East Coast, 26–34 days by sea to Rotterdam or Hamburg and 28–35 days by sea to the UK. A shipment loaded on 22 January to the US West Coast would therefore typically arrive in mid-February, before the factory has fully restarted.

Also check:  Which fabric is best for you, micromodal or Tencel: A Manufacturer's Comparison

After the holiday, offices reopen on Sunday 14 February 2027. Plan on a ramp-up period before lines reach normal output, and do not schedule a post-holiday order to start bulk on the first working day. A realistic plan for a new post-holiday order places bulk start after the Lantern Festival on 20 February and first shipments in March, adjusted to what your supplier confirms.

Common mistakes around Chinese New Year

  • Planning to the public holiday instead of the supplier’s dates. The last loading day is earlier than 5 February.
  • Approving samples late. A two-week approval delay in December can push an order past the holiday.
  • Changing specifications in January. A new colour or label after bulk starts can stop a line that has no slack left.
  • Forgetting trims. Labels, elastic and packaging have their own suppliers and closures.
  • No post-holiday plan. If an order slips, decide early whether to air-freight part of it or move the launch date.
  • Ignoring the second wave. Many brands place orders right after the holiday, so post-holiday capacity can be tight too.

What a factory should confirm in writing

Ask for these before you pay the deposit:

  1. Last date for material delivery to the factory.
  2. Last loading date for finished goods.
  3. Office reopening date and expected full-production date.
  4. Which approvals are still open and their deadlines.
  5. Whether fabric for repeat orders can be reserved before the holiday.

Finetex confirms the production schedule in writing before the deposit is paid, as stated on our shipping and product pages. Our clothing factory sourcing guide covers the wider approval chain, and our post on factory capacity in peak season explains how holiday periods affect booking.

What is fact, what is advice and what is uncertain

Fact: the 2027 holiday and make-up working days are from the State Council notice published on 5 November 2026; Finetex lead times and transit times are from Finetex’s published pages, read on 11 November 2026.

Advice: the two-week loading buffer, the 90/60/30-day plan and the post-holiday timing are planning recommendations, not rules.

Uncertain: individual factory closure lengths, worker return dates and freight conditions vary every year. Confirm dates with your supplier and forwarder.

Related reading

Frequently asked questions

When is Chinese New Year 2027?

Chinese New Year’s Day is Saturday 6 February 2027. The official public holiday runs from Friday 5 February to Saturday 13 February 2027, with make-up working days on 31 January and 14 February.

When should I place an order to ship before Chinese New Year 2027?

For most knitwear orders, approve pre-production samples and pay the deposit by early December 2026, and plan to load goods around late January 2027. Confirm the supplier’s last loading date.

How long are Chinese factories closed for the New Year?

The public holiday is nine days in 2027, but many factories need extra time before and after for workers to travel and lines to restart. Ask each supplier for its own dates in writing.

Also check:  How is Indonesia's clothing industry transforming through innovation and sustainable production: A Manufacturer's Walkthrough

Can I ship by air if my order runs late?

Yes, if production finishes before the factory closes and air space is available. Air freight costs several times more per kilogram, so decide early whether a partial air shipment is worth it.

When does production return to normal after the holiday?

Offices reopen on 14 February 2027, but full output usually takes longer. For new orders, plan bulk start after the Lantern Festival on 20 February and confirm with your supplier.

Sources

Lock your pre-holiday order

Send us your styles, quantities and required arrival date. We will confirm in writing whether the order can load before Chinese New Year 2027 and what has to be approved by when.

Request a quote or read our clothing factory sourcing guide.

Keep reading

More factory-floor notes for brand owners

Request a sample & pricing information

Send us your tech pack, target price or a reference sample — we reply with a quotation, a realistic lead time and a fabric recommendation within one working day.

  • Free sampling plan & cost breakdown
  • MOQ from 300 pcs per style
  • Reply within 1 working day
Scroll to Top